Science & Health Refresh

Air Quality Reports - Farquharson

Inspection Report 34 - visual-air clearance Feb 26 2018 (pdf)
Inspection Report 33 - Site Set up Feb 22 2018 (pdf)
Inspection Report 32 - Site Set up Feb 20 2018 (pdf)
Inspection Report 31 - Occupied Air Monitoring Jan 11 2017  (pdf)
Inspection Report 30 - Occupied Air Monitoring Dec 12 2017 (pdf)
Inspection Report 29 - Occupied Air Monitoring Nov 10 2017 (pdf)
Inspection Report 28 - Occupied Air Monitoring Nov 3 2017 (pdf)
Inspection Report 27 - Occupied Air Monitoring Oct 27 2017 (pdf)
Inspection Report 26 - Occupied Air Monitoring Oct 18 2017 (pdf)
Inspection Report 25 - Occupied Air Monitoring Oct 11 2017 (pdf)
Inspection Report 24 - Occupied Air Monitoring Oct 5 2017 (pdf)
Inspection Report 23 - Occupied Air Monitoring Sept 28 2017 (pdf)
Inspection Report 22a - Mechanical Room 007 Air Monitoring Clearance (pdf)
Inspection Report 22 - Occupied Air Monitoring Aug 11 2017 (pdf)
Inspection Report 21 - Mechanical Room 007 Visual Clearance (pdf)
Inspection Report 20 - Mechanical Room 007 Precontamination (pdf)
Inspection Report 19 - Penhouse Mechanical air Clearance - Repeated (pdf)
Inspection Report 18 - Penhouse Mechanical air Clearance (pdf)
Inspection Report 17 - Penhouse Mechanical Visual Clearance (pdf)
Inspection Report 16 - Penhouse Mechanical Visual Clearance (pdf)
Inspection Report 16 - Occupied Air Monitoring Aug 4 2017 (pdf)
Inspection Report 15 - Penhouse Mechanical Precontamination (pdf)
Inspection Report 14 - Occupied Air Monitoring July 27 2017 (pdf)
Inspection Report 12 - Occupied Air Monitoring July 11 2016 (pdf)
Inspection Report 11-s corridor at 011 precontam (pdf)
Inspection Report 11a-s corridor at 011 Visual Clearance (pdf)
Inspection Report 10-occupied air monitoring (pdf)
Inspection Report 9-corridor at 011 visual and air clearance (pdf)
Inspection Report 9 (pdf)
Inspection Report 8-corridor at 011 precontam (pdf)
Inspection Report 7-Occupied Air Monitoring (pdf)
Inspection Report 6 -Occupied Air Monitoring (pdf)
Inspection Report 5 - Room 011 007 and others (pdf)
Inspection Report 4 - West Wing Air Monitoring (pdf)
Inspection Report 4 - Occupied Air Monitoring (pdf)
Inspection Report 3 - Room 233A (pdf)
Inspection Report 3 - Room 233A clearance  (pdf)
Inspection Report 2 Room 233A (pdf)
Inspection Report 2 Room 233A precontam (pdf)
Inspection Report 1-Testing of suspect ACM (pdf)

 

Faculty of Science 
Ray Jayawardhana Dean, Faculty of Science rayjay@yorku.ca
Sylvie Morin Associate Dean, Research & Graduate Education sciadres@yorku.ca
Doriano D'Angelo Facilities Manager, Faculty of Science & Engineering doriano@yorku.ca
Faculty of Health
Paul McDonald Dean, Faculty of Health healthdn@yorku.ca
Mazyar Fallah Associate Dean, Research & Innovation hhadri@yorku.ca
Tom Hodgson Manager, Physical Resources,
Health & Safety, Research Support
thodgson@yorku.ca
Campus Services and Business Operations
Richard Francki Assistant Vice-President rfrancki@yorku.ca 
Ron Ogata Project Director rogata@yorku.ca 
Adriano Morassutti Assistant Project Manager adrianom@yorku.ca 
Lassonde School of Engineering
Richard Wildes Associate Professor and Chair,
Department of Electrical Engineering
wildes@cse.yorku.ca
Ed Secnik Manager, Health, Safety, Security and Facilities edward.secnik@lassonde.yorku.ca

Installation of Air Handling Units -

Installation of air handling units at Farquharson  Air handling units at Farquharson

Project Updates

Farquharson Update 38 - April 13, 2018

Progress

  • Continued boarding and taping on 1st, 2nd and 3rd floor.
  • Installation of exterior windows commenced.
  • Ceiling installation outside Mechanical Room 007 will continue.
  • Mechanical piping installation continued in corridor outside Mechanical Room 007.
  • Continued installation of HVAC duct work on 1st, 2nd and 3rd floor.
  • Continued installation of plumbing rough-in on all floors.
  • Continued installation of new Fire Alarm system along basement corridors.
  • Generator installed on new concrete pad.
  • Installation of exterior penthouse panels continued.
  • New Heat Recovery unit installed on Penthouse roof.

Upcoming

  • Installation of sprinkler branches will continue.
  • Concrete pour for entrance extension scheduled for next week.
  • Plumbing rough-in will continue on 1st,2nd and 3rd floors.
  • Continue installation of HVAC duct work on 1st, 2nd and 3rd floor.
  • Installation of drywall studs and drywall for 1st, 2nd and 3rd floor will continue.
  • Installations of main electrical feeders will continue.
  • Continue installation of new Fire Alarm system along basement and West wing corridors.
  • Continue installation of Penthouse roof panels.
  • Continue installation of exterior windows.

Farquharson Update 37 - March 23, 2018

Progress

  • Continued installation of drywall studs on 1st, 2nd and 3rd floor.
  • Ceiling installation outside Mechanical Room 007 will continue.
  • Mechanical piping installation continued in corridor outside Mechanical Room 007.
  • Continued installation of HVAC duct work on 1st, 2nd and 3rd floor.
  • Continued installation of new Fire Alarm system along basement corridors.

 

Upcoming

  • Installation of sprinkler mains and branches will continue.
  • Plumbing rough-in will continue on 1st,2nd  and 3rd floors.
  • Continue installation of HVAC duct work on 1st, 2nd and 3rd floor.
  • Installation of drywall studs and drywall for 1st, 2nd and 3rd floor will continue.
  • Installations of main electrical feeders will continue.
  • Continue installation of new Fire Alarm system along basement corridors.
  • Commence installation of Penthouse exterior panels.
  • Commence excavation of generator pad.

Farquharson Update 36 - March 9, 2018

Progress

  • Continued installation of drywall studs on 1st, 2nd and 3rd floor.
  • Ceiling installation outside Mechanical Room 007 will continue.
  • Abatement completed in Main Mechanical room 007.
  • Installation of structural steel at Main Entrance completed.
  • Mechanical piping installation continued in corridor outside Mechanical Room 007.
  • Continued installation of HVAC duct work on 1st, 2nd and 3rd floor.
  • Spray fireproofing for exterior shafts completed.
  • Started cleaning brick and precast on all levels.
  • Commenced installation of new Fire Alarm system along basement corridors.

Upcoming

  • Installation of sprinkler mains and branches will continue.
  • Plumbing rough-in will continue on 1st and 2nd floors.
  • Continue installation of HVAC duct work on 1st, 2nd and 3rd floor.
  • Installation of drywall studs for 1st, 2nd and 3rd floor will continue.
  • Mechanical piping installation will continue in corridor outside Mechanical room 007.
  • Installations of main electrical feeders will continue.
  • Continue installation of new Fire Alarm system along basement corridors.

Farquharson Update 35 - February 16, 2018

Progress

  • Continued installation of drywall studs on 1st, 2nd and 3rd floor.
  • Mechanical piping installation continued in corridor outside Mechanical room 007.
  • Continued installation of HVAC duct work on 1st, 2nd and 3rd floor.
  • Spray fireproofing for exterior shafts completed.
  • Started cleaning brick and precast on all levels.
  • Commenced installation of new Fire Alarm system along basement corridors.

Upcoming

  • Installation of sprinkler mains and branches will continue.
  • Plumbing rough-in will continue on 1st and 2nd floors.
  • Installation of structural steel for new front entrance will commence with steel delivery on February 21st.
  • Continue installation of HVAC duct work on 1st, 2nd and 3rd floor.
  • Installation of drywall studs for 1st, 2nd and 3rd floor will continue.
  • Mechanical piping installation will continue in corridor outside Mechanical room 007.
  • Installations of main electrical feeders will continue.
  • Continue installation of new Fire Alarm system along basement corridors.
  • Abatement of main mechanical units in Mechanical Room 007 will commence.

Farquharson Update 34 - February 2, 2018

Progress

  • Pre-cast columns cut at Northwest and Southeast corners on 1st, 2nd and 3rd floor.
  • Continued installation of drywall studs on 1st, 2nd and 3rd floor.
  • Mechanical piping installation continued in corridor outside Mechanical room 007.
  • Continued installation of HVAC duct work on 1st, 2nd and 3rd floor.
  • Completed plumbing piping in basement.
  • Structural steel for penthouse level was installed.
  • Demolition of elevator continued.
  • Brick infill of doorway openings continued on all floors.

Upcoming

  • Installation of sprinkler mains and branches will continue.
  • Plumbing rough-in will continue on 1st and 2nd floors.
  • Mason to commence extension of elevator shaft to penthouse.
  • Continue installation of HVAC duct work on 1st, 2nd and 3rd floor.
  • Installation of drywall studs for 1st, 2nd and 3rd floor will continue.
  • Mechanical piping installation will continue in corridor outside Mechanical room 007.
  • Installations of main electrical feeders will continue.

Farquharson Update 33 - January 12, 2018

Progress

  • New generator pad North of Greenhouse completed.
  • Excavation south of lobby entrance has been backfilled.
  • Cut pre-cast columns at Northwest and Southeast corners on 1st, 2nd and 3rd floor.
  • Continued installation of drywall studs on 1st, 2nd and 3rd floor.
  • Mechanical piping installation continued in corridor outside Mechanical room 007.
  • Continued installation of HVAC duct work on 1st, 2nd and 3rd floor.
  • Continued piping work in basement labs for new labs on 1st floor.
  • Structural steel for penthouse level was installed.
  • Demolition of elevator continued.
  • Brick infill of doorway openings continued on all floors.

Upcoming

  • Installation of metal roof decking will commence.
  • Commence lighting rough-in on 1st floor.
  • Will continue fireproofing structural beams on 1st floor.
  • Brick infill of doorway openings will continue on all floors.
  • Continue piping work in basement labs for new labs on 1st floor as scheduled with occupants.
  • Continue installation of HVAC duct work on 1st, 2nd and 3rd floor.
  • Installation of drywall studs for 1st, 2nd and 3rd floor will continue.
  • Mechanical piping installation will continue in corridor outside Mechanical room 007.
  • Installations of main electrical feeders will continue.

Farquharson Update 32 - December 7

Progress

  • Excavation of generator pad North of Greenhouse completed
  • Excavation south of lobby entrance completed
  • Continued fireproofing structural beams on 1st floor
  • Continued installation of drywall studs on 1st floor
  • Mechanical piping installation continued in corridor outside Mechanical room 007
  • Continued installation of HVAC duct work on 1st floor
  • Commenced piping work in basement labs for new labs on 1st floor

Upcoming

  • Start masonry work on door fill-ins on 1st floor
  • Commence lighting rough-in on 1st floor
  • Remove stained ceiling tiles in basement corridors
  • Will continue fireproofing structural beams on 1st floor
  • Concrete saw cutting of new doorways on 1st, 2nd and 3rd floors will continue
  • Continue piping work in basement labs for new labs on 1st floor as scheduled with occupants
  • Continue installation of HVAC duct work on 1st floor
  • Installation of drywall studs for 1st and 2nd floors
  • Mechanical piping installation will continue in corridor outside Mechanical room 007
  • Installations of main electrical feeders will continue

Farquharson Update 31 - November 24

Progress

  • Demolition of labs on all floors completed
  • Continued concrete grinding of 2nd and 3rd floors
  • Mechanical piping installation continued in corridor outside Mechanical room 007
  • Concrete pour is completed for 1st, 3rd and penthouse floors
  • Continue demolition of South Main Entrance elevation
  • Continued installation of HVAC duct work on 1st floor
  • Commenced piping work in basement labs for new labs on 1st floor

Upcoming

  • Wednesday, November 29th crane lift scheduled to place air handling units on Farquharson roof.  Exercise will require closure of Lumbers parking lot for a full day 7:00 am to 6:00 pm
  • Excavate generator pad North of Greenhouse start of next week
  • Excavate south of lobby entrance
  • Fireproofing structural beams on 1st floor
  • Concrete saw cutting of new doorways on 1st, 2nd and 3rd floors will continue
  • Continue piping work in basement labs for new labs on 1st floor as scheduled with occupants
  • Continue installation of HVAC duct work on 1st floor
  • Installation of drywall studs for 1st floor
  • Mechanical piping installation will continue in corridor outside Mechanical room 007
  • Installations of main electrical feeders will continue

Farquharson Update 30 - November 17

Progress

  • Demolition of labs on all floors completed
  • Continued concrete grinding of 2nd and 3rd floors
  • Mechanical piping installation continued in corridor outside Mechanical room 007
  • Steel decking installed on 1st and 3rd floors
  • Continue demolition of South Main Entrance elevation
  • Continued installation of HVAC duct work on 1st floor
  • Commenced piping work in basement labs for new labs on 1st floor

Upcoming

  • Concrete saw cutting of new doorways on 1st, 2nd and 3rd floors will continue
  • Continue piping work in basement labs for new labs on 1st floor as scheduled with occupants
  • Continue installation of HVAC duct work on 1st floor
  • Continue electrical and plumbing investigation in basement.  Concrete pump truck will set up on the south side of Farquharson
  • Demolition of South main Entrance elevation will continue
  • Concrete pour is scheduled for 1st, 3rd floors and penthouse floors next week
  • Concrete grinding of floors will continue on all floors
  • Mechanical piping installation will continue in corridor outside Mechanical room 007
  • Installations of main electrical feeders will continue

Farquharson Update 29 - November 10

Progress

  • Demolition of labs on all floors completed
  • Continued concrete grinding of 2nd and 3rd floors
  • Mechanical piping installation continued in corridor outside Mechanical room 007
  • Demolition of Penthouse roof completed
  • Concrete saw cutting of new doorways continued on 1st, 2nd and 3rd floors
  • Continue demolition of South Main Entrance elevation
  • Started installation of HVAC duct work on 1st floor

Upcoming

  • Concrete saw cutting of new doorways on 1st, 2nd and 3rd floors will continue
  • Steel decking will be installed on 1st and 3rd floors
  • Commence installation of HVAC duct work on 1st floor
  • Continue electrical and plumbing investigation in basement.  Concrete pump truck will set up on the south side of Farquharson
  • Demolition of South main Entrance elevation will continue
  • Concrete pour is scheduled for 1st and 3rd floors
  • Concrete grinding of floors will continue on all floors
  • Mechanical piping installation will continue in corridor outside Mechanical room 007
  • Installations of main electrical feeders will continue

Farquharson Update 28 - November 3

Progress

  • Demolition continued throughout construction area
  • Concrete grinding of 1st floor completed
  • Mechanical piping installation continued in corridor outside Mechanical room 007
  • Demolition of Penthouse roof continued
  • Concrete saw cutting of new doorways continued on 1st, 2nd and 3rd floors

Upcoming

  • Concrete saw cutting of new doorways on 1st, 2nd and 3rd floors will continue
  • Commence installation of HVAC duct work on 1st floor
  • Continue electrical and plumbing investigation in basement
  • Demolition of South main Entrance elevation will commence
  • Demolition of labs on all floors will continue
  • Concrete grinding of floors will commence on 2nd and 3rd floors
  • Continue demolition of Penthouse roof
  • Mechanical piping installation will continue in corridor outside Mechanical room 007
  • Installations of main electrical feeders will continue

Farquharson Update 27 - October 27

Progress

  • Demolition continued throughout construction area
  • Construction of temporary penthouse weather protection continued with installation of roof system
  • Mechanical piping installation continued in corridor outside Mechanical room 007
  • Demolition of Penthouse roof continued
  • Structural work commenced in corridor outside Mechanical room 007
  • Concrete saw cutting of new doorways continued on 1st, 2nd and 3rd floors

Upcoming

  • Concrete saw cutting of new doorways on 1st, 2nd and 3rd floors will continue
  • Demolition of labs on all floors will continue
  • Concrete grinding of floors will commence on 1st and 2nd floors
  • Continue demolition of Penthouse roof
  • Mechanical piping installation will continue in corridor outside Mechanical room 007
  • Installations of main electrical feeders will continue

Farquharson Update 26 - October 20

Progress

  • Demolition continued throughout construction area
  • Construction of temporary penthouse weather protection continued with installation of roof system
  • Mechanical piping installation continued in corridor outside Mechanical room 007
  • Demolition of Penthouse roof continued
  • Structural work commenced in corridor outside Mechanical room 007

Upcoming

  • Concrete saw cutting of new doorways on 1st, 2nd and 3rd floors
  • Demolition of labs on all floors will continue
  • Installation of temporary penthouse weather protection will continue
  • Continue demolition of Penthouse roof
  • Mechanical piping installation will continue in corridor outside Mechanical room 007
  • Installations of main electrical feeders will continue

Farquharson Update 25 - October 12

Progress

  • Demolition continued throughout construction area
  • Construction of temporary penthouse weather protection continued with installation of roof system
  • Mechanical piping installation continued in corridor outside Mechanical room 007
  • Demolition of Penthouse roof continued
  • Structural work commenced in corridor outside Mechanical room 007

Upcoming

  • Concrete saw cutting of new doorways on 1st, 2nd and 3rd floors
  • Demolition of labs on all floors will continue
  • Installation of temporary penthouse weather protection will continue
  • Continue demolition of Penthouse roof
  • Structural work to commence in corridor outside Mechanical room 007
  • Mechanical piping installation will continue in corridor outside Mechanical room 007
  • Installations of main electrical feeders will continue

Farquharson Update 24 - October 6

Progress

  • Demolition continued throughout construction area
  • Construction of temporary penthouse weather protection continued with installation of roof system
  • Mechanical piping installation continued in corridor outside Mechanical room 007
  • Demolition of Penthouse roof continued
  • Structural work commenced in corridor outside Mechanical room 007
  • Completed finishes in Basement Room 011

Upcoming

  • Concrete saw cutting of new doorways on 1st, 2nd and 3rd floors
  • Demolition of labs on all floors will continue
  • Installation of temporary penthouse weather protection will continue
  • Continue demolition of Penthouse roof
  • Structural work to commence in corridor outside Mechanical room 007
  • Mechanical piping installation will continue in corridor outside Mechanical room 007
  • Installations of main electrical feeders will continue

Farquharson Update 23 - Sept 29

Progress

  • Demolition continued throughout construction area
  • Construction of temporary penthouse weather protection continued with installation of roof system
  • Mechanical piping installation continued in corridor outside Mechanical room 007
  • Demolition of Penthouse roof continued
  • Structural work commenced in corridor outside Mechanical room 007

Upcoming

  • Hoarding fence on the South side will be returned to previous location now that Yorkfest activities have concluded
  • Concrete saw cutting of new doorways on 1st, 2nd and 3rd floors
  • Complete finishes in Basement Room 011
  • Demolition of labs on all floors will continue
  • Installation of temporary penthouse weather protection will continue
  • Continue demolition of Penthouse roof
  • Structural work to commence in corridor outside Mechanical room 007
  • Continue removing block shaft walls on 3rd floor
  • Mechanical piping installation will continue in corridor outside Mechanical room 007
  • Installations of main electrical feeders will continue

Farquharson Update 22 - Sept 22

Progress

  • Demolition continued throughout construction area
  • Construction of temporary penthouse weather protection continued with installation of roof system
  • Mechanical piping installation continued in corridor outside Mechanical room 007
  • Demolition of Penthouse roof commenced
  • Structural work commenced in corridor outside Mechanical room 007

Upcoming

  • Hoarding fence on the South side will temporarily be moved towards building to accommodate Yorkfest activities
  • Complete finishes in Basement Room 011
  • Demolition of labs on all floors will continue
  • Installation of temporary penthouse weather protection will continue
  • Continue demolition of Penthouse roof
  • Structural work to commence in corridor outside Mechanical room 007
  • Continue removing block shaft walls on 3rd floor
  • Mechanical piping installation will continue in corridor outside Mechanical room 007
  • Installations of main electrical feeders will continue

Farquharson Update 21 - Sept 15

Progress

  • Demolition continued throughout construction area
  • Construction of temporary penthouse weather protection commenced
  • Mechanical piping installation continued in corridor outside Mechanical room 007
  • Coring on 1st Floor above Room 011 completed
  • Demolition of Penthouse roof commenced
  • Structural work commenced in corridor outside Mechanical room 007

Upcoming

  • Demolition of labs on all floors will continue
  • Installation of temporary penthouse weather protection will continue
  • Continue demolition of Penthouse roof
  • Structural work to commence in corridor outside Mechanical room 007
  • Continue removing block shaft walls on 3rd floor
  • Mechanical piping installation will continue in corridor outside Mechanical room 007
  • Installations of main electrical feeders will continue

Farquharson Update 20 - Sept 8

Progress

  • Non-structural demolition continued throughout construction area
  • Block wall removals completed on Third floor
  • Demolition of stairs and stair shear walls completed
  • Mechanical piping installation continued in corridor outside Mechanical room 007
  • S8 removal in Penthouse completed
  • Demolition of Penthouse roof commenced

Upcoming

  • Demolition of labs on all floors will continue
  • Structural work to commence in corridor outside Mechanical room 007
  • Continue removing block shaft walls on 3rd floor
  • Mechanical piping installation will continue in corridor outside Mechanical room 007
  • Installations of main electrical feeders will continue
  • Continue demolition of Penthouse roof
  • Coring on First floor above Room 011

Farquharson Update 19 - Sept 1

Progress

  • Non-structural demolition continued throughout construction area
  • Block wall removals complete on third floor
  • Demolition of stairs and stair shear walls continued
  • Completing infilling floors of shaft walls on 1st floor
  • Mechanical piping work outside Mechanical room 007 continued
  • S8 removal in Penthouse commenced

Upcoming

  • Demolition of labs on all floors will continue
  • Structural work to commence in corridor outside Mechanical room 007
  • Continue infilling floors of shaft walls on 2nd floor
  • Mechanical piping installation will commence in corridor outside Mechanical room 007
  • Installations of main electrical feeders will commence
  • Demolition of stairs and stair shear walls will continue
  • Continue removal of S8 in Penthouse
  • Commence demolition of Penthouse roof

Farquharson Update 18 - Aug 25

Progress

  • Non-structural demolition continued throughout construction area
  • Block wall removals complete on ground floor
  • Demolition of stairs and stair shear walls continued
  • Tarping and hoarding set up in Basement corridor outside Mechanical room 007 to accommodate Mechanical piping work leading to Room 011
  • S8 removal in Penthouse commenced

Upcoming

  • Demolition of labs on all floors will continue
  • Structural work to commence in corridor outside Mechanical room 007
  • Continue removing block shaft walls on 3rd floor
  • Mechanical piping installation will commence in corridor outside Mechanical room 007
  • Installations of main electrical feeders will commence
  • Demolition of stairs and stair shear walls will continue
  • Continue removal of S8 in Penthouse
  • Commence demolition of Penthouse roof

Farquharson Update 17 - Aug 18

Progress

  • Non-structural demolition continued throughout construction area
  • Block wall removals complete on ground floor
  • Demolition of stairs and stair shear walls continued
  • Sprinkler main installation commencing on ground floor
  • Interior block walls removed on 3rd floor
  • Duct work in shaft wall outside 011 completed
  • S8 removal in Penthouse commenced

Upcoming

  • Demolition of labs on all floors will continue
  • Continue removing block shaft walls on 2nd and 3rd floors
  • Mechanical piping installation will commence in corridor outside Mechanical room 007
  • Installations of main electrical feeders will commence
  • Demolition of stairs and stair shear walls will continue
  • Continue removal of S8 in Penthouse
  • Commence demolition of Penthouse roof

Farquharson Update 16 - Aug 11

Progress

  • Non-structural demolition continued throughout construction area
  • Demolition of labs on all floors complete
  • -80 Freezers relocated in order to install structural components of the building
  • Concrete infills ground floor corridors formed and poured
  • Sprinkler main installations on ground floor
  • Interior block walls being removed on 3rd floor
  • Central stair demolition, stair, stair landing, and stair shear wall removals

Upcoming

  • Non-structural demolition continued throughout construction area
  • Continue removing block walls on 3rd floor
  • Fire alarm work will continue on ground floor and 2nd floors
  • Installations of main electrical feeders will continue
  • Central stair demolition ongoing, stair, stair landing, and stair shear wall removals

Farquharson Update 15 - Aug 4

Progress

  • Non-structural demolition continued throughout construction area
  • -80 Freezers relocated in order to install structural components of the building
  • Sprinkler main installations on ground floor
  • Interior block walls removed on 2nd floor
  • Interior block walls being removed on 3rd floor
  • Cutting and coring shaft walls of 011 to connect mechanical in corridors complete

Upcoming

  • Demolition of labs on all floors will continue
  • Continue removing block walls on 3rd floor
  • Fire alarm work will continue on ground floor and 2nd floors
  • Installations of main electrical feeders will continue
  • Central stair demolition starts August 8/17, stair, stair landing, and stair shear wall removals
  • Compressed air shutdown affecting the entire building for 15 minutes August 8/17 at 8:15AM to cap the line

Farquharson Update 14 - July 28

Progress

  • Non-structural demolition continued throughout construction area
  • Block wall removals complete on ground floor
  • Sprinkler main installation commencing on ground floor
  • Interior block walls are being removed on 2nd floor
  • Cutting and coring shaft walls of 011 to connect mechanical in corridors
  • RO piping complete in basement

Upcoming

  • Demolition of labs on all floors will continue
  • Continue removing block walls on 2nd floor and demolishing block walls on 3rd floor
  • Fire alarm work will commence on ground floor and 2nd floors
  • Installations of main electrical feeders will commence
  • Demolition of stairs and stair shear walls will commence
  • Ductwork in Room 043 per notification

Farquharson Update 13 - July 21

Progress

  • Non-structural demolition continued throughout construction area
  • All service shaft walls have been removed on 1st floor
  • Fume hood exhaust duct work removed from roof
  • Brick veneer was removed from centre stair
  • Interior block walls were removed from labs on 2nd floor
  • RO piping was installed along basement north corridor

Upcoming

  • Demolition of labs on all floors will continue
  • Continue work on RO water piping in basement
  • Cutting and coring shaft walls of 011 to connect mechanical in corridors
  • Continue demolishing block walls on 2nd and 3rd floors
  • Removal of brick veneer from central stair will continue
  • Demolition of stairs and stair shear walls will commence
  • Removal of sanitary lines within basement labs as per notification

Farquharson Update 12 - July 14

Progress

  • Non-structural demolition continued throughout construction area
  • Completed electrical shutdowns for basemen circuit tracing as per released notification
  • Completed exterior hoist installation at northeast entrance
  • Removal of abandoned Fume Hood exhaust duct on Penthouse roof continued
  • Completed shutdown of building steam system to cap service to S3, S8 and autoclave rooms
  • Demolished remaining block partitions on first floor and removed concrete curbs from service shafts
  • RO piping was installed along basement north corridor

Upcoming

  • Demolition of labs on all floors will continue
  • Continue work on RO water piping in basement
  • Investigate piping and duct work in Farquharson 011 ceiling
  • Demolished penthouse duct work will be removed from the roof and taken off site
  • Removal of brick veneer from central stair will continue
  • Remaining service shaft walls over 010A, 016, 021 and 047 will be removed Monday, July 17th
  • Block wall partition removal will commence on Second floor

Farquharson Update 11 - July 7

Progress

  • Non-structural demolition continued throughout construction area
  • Completed scheduled power shutdowns in basement labs for temporary power tie-in for construction site
  • Removal of S3 from Mechanical room 007 continued
  • Removal of abandoned Fume Hood exhaust duct on Penthouse roof continued
  • Installation of exterior hoist continued
  • RO piping was installed along basement north corridor

Upcoming

  • Demolition of labs on all floors will continue
  • Continue exterior hoist installation at northeast entrance
  • Continue S3 demolition and removal
  • Continue work on RO water piping in basement
  • Investigate piping and duct work in Farquharson 011 ceiling
  • Electrical shutdowns for basement to commence July 11th for circuit tracing as per released notification
  • Shutdown of building steam system scheduled for Thursday, July 13th to cap service to S3, S8 and autoclave rooms
  • Demolished penthouse duct work will be removed from the roof and taken off site
  • Demolition of remaining block partitions on first floor and removal of concrete curbs will be scheduled this week. Notification to be sent to occupants

York University Farquharson Building - Basement Circuit Tracing(2)

Farquharson Update 10 - June 30

Progress

  • Non-structural demolition continued throughout construction area
  • Completed scheduled power shutdowns in basement labs for temporary power tie-in for construction site
  • Completed scheduled natural gas, compressed air and domestic water piping removal in basement labs
  • Removal of S3 from Mechanical room 007 continued
  • Removal of abandoned Fume Hood exhaust duct on Penthouse roof continued
  • Installation of exterior hoist continued
  • RO water supply for West wing switched to Lumbers feed

Upcoming

  • Demolition of labs on all floors will continue
  • Continue exterior hoist installation at northeast entrance
  • Continue S3 demolition and removal
  • Commence work on RO water piping in basement
  • Investigate piping and duct work in Farquharson 011 ceiling
  • Electrical shutdowns for basement to commence July 4th for circuit tracing as per released notification

York University Farquharson Building - Basement Circuit Tracing

Farquharson Update 9 - June 23

Progress

  • Non-structural demolition continued throughout construction area
  • Intermediate block partitions removed on first floor
  • Telecom cut over complete
  • Removal of S3 from Mechanical room 007 continued
  • Removal of abandoned Fume Hood exhaust duct on Penthouse roof continued
  • Installation of exterior hoist continued
  • Ceiling for Farquharson 011 removed

Upcoming

  • Demolition of labs on all floors will continue
  • Continue exterior hoist installation at northeast entrance
  • Continue S3 demolition and removal
  • Commence work on RO water piping in basement
  • Investigate piping and duct work in Farquharson 011 ceiling
  • Electrical shutdowns for basement panels as per released notification
  • Domestic water, natural gas and compressed air shutdown in basement to cut and cap services as per notification

Farquharson Update 8 - June 16

Progress

  • Non-structural demolition continued throughout construction area
  • Lab casework removal continued on all floors
  • Telecom room was moved to new temporary location
  • Removal of S3 from Mechanical room 007
  • Removal of abandoned Fume Hood exhaust duct on Penthouse commenced
  • Exterior hoist foundation completed
  • Ceiling for Farquharson 011 removed

Upcoming

  • Complete Telecom cut over
  • Demolition of labs on all floors will continue
  • Continue exterior hoist installation at northeast entrance
  • Continue S3 demolition and removal
  • Commence work on RO water piping
  • Investigate piping and duct work in Farquharson 011 ceiling
  • Removal of block partitions, commencing on First floor

Farquharson Update 7 - June 9

Progress

  • Non-structural demolition continued throughout construction area
  • Lab casework removal continued on all floors
  • Work completed on exterior duct work on north elevation
  • Work continued on installing sprinkler line down basement north corridor
  • Scheduled compressed air shutdown completed
  • Exterior hoist foundation completed

Upcoming

  • Continue work on sprinkler riser for west wing
  • Demolition of labs on all floors will continue
  • Continue exterior hoist installation at northeast entrance
  • Continue S3 demolition and removal

Farquharson Update 6 - June 2

Progress

  • Non-structural demolition continued throughout construction area
  • Lab casework removal continued on all floors
  • Work continued on exterior duct work on north elevation
  • Temporary duct work for fume hoods completed in labs 016, 018 and 021
  • Work continued on installing sprinkler line down basement north corridor
  • Scheduled electrical power shutdown completed
  • Temporary compressed air tie-ins completed in labs 038 and 022

Upcoming

  • Continue work on sprinkler riser for west wing
  • Continue work on exterior duct work on north elevation
  • Demolition of labs on all floors will continue
  • Scheduled building wide compressed air shutdown for Monday, June 5th, 8:00 am to 11:00 am

Farquharson Update 5 - May 26

Progress

  • Non-structural demolition continued throughout construction area
  • Lab casework removal continued on all floors
  • Work continued on exterior duct work on north elevation
  • Work continued on installing sprinkler line down basement north corridor.

Upcoming

  • Scheduled electrical power shutdown, will not affect west wing occupants
  • Continue work on sprinkler line down basement north corridor
  • Continue work on exterior duct work on north elevation
  • Scheduled work in basement labs
  • Demolition of labs on all floors will continue.

Farquharson Update 4 - May 19

Progress

  • Non-structural demolition continued throughout construction area
  • Lab casework removal continued on all floors
  • Work continued on exterior duct work on north elevation
  • Construction trailers have power and telecommunications
  • Work commenced on installing sprinkler line down basement north corridor.

Upcoming

  • Continue work on sprinkler line down basement north corridor
  • Continue work on exterior duct work on north elevation
  • Demolition of labs on all floors will continue.

Farquharson Update 3 - May 12

Progress

  • Exterior hoarding and interior hoarding completed
  • Lab casework removal commenced on second and third floors
  • Fencing installed around perimeter of construction trailers
  • Noise and vibration testing was completed Monday, May 8th (evening), awaiting results.

Upcoming

  • Delivery of exterior hoist for northeast corner expected week of May 15th
  • Non-structural demolition will continue on all floors
  • Work on temporary exterior ductwork on north elevation will commence
  • Electrical tie-in to construction trailers will take place on May 13th and be completed for Monday, May 15th.

Farquharson Update 2 - May 5

Progress

  • Hoarding on south side exterior installed
  • Internal hoarding on first floor completed
  • Site trailers delivered to Vanier Green
  • Lab casework removal commenced on first floor

Upcoming

  • Hoarding installation will continue
  • Site trailer installation will continue
  • Demolition of labs will commence on second and third floors
  • Noise and vibration will take place Monday afternoon

Farquharson Update 1- April 28

FARQUHARSON SCIENCE AND HEALTH RENEWAL PROJECT

On May 1, 2017 the Construction Manager will be erecting hoarding inside and outside of the Farquharson Life Sciences Building. The shaded areas on the First, Second and Third floor will not be accessible to the public. The passenger elevator is in the shaded area and therefore will not be available for public use. The Basement washroom will remain operational during the project and the Lumbers washrooms will be available to the Farquharson occupants.

During the first week in May Gillam Group will commence work on their site trailer compound on Vanier Green. At this point the Construction Manager will have control of the Farquharson loading dock and delivery access will have to be coordinated with them.

Site Logistics Plan for Farquharson

Contact:           Adriano Morassutti, Assistant Project Manager, CSBO, adrianom@yorku.ca

Ron Ogata, Project Director, CSBO, rogata@yorku.ca

Chemistry

Air Barrier Remediation
As part of the Science Building Renewal Project we will be repairing the air barrier issue around the windows in the Chemistry Building.  Stephenson Engineering will be in on Friday, March 17th to perform a preliminary investigation. Small test openings will be cut into the wall and window sills may be removed at the location of the wall opening.  Once testing is complete all patching and repairs will be scheduled.

Chemistry Update 10 - December 15

Progress

  • Exterior caulking completed on the north, south and east elevations and west elevation

Upcoming

  • 2nd floor offices, drywall infills will be taking place above the ceiling.  Spray foam will be installed above the ceilings at the exterior wall

Chemistry Update 9 - December 7

Progress

  • Exterior caulking completed on the north, south and east elevations and west elevation

Upcoming

  • 2nd floor offices, drywall infills will be taking place above the ceiling.  Spray foam will be installed above the ceilings at the exterior wall

Chemistry Update 8 - December 1

Progress

  • Exterior caulking completed on the north, south and east elevations and west elevation

Upcoming

  • 2nd floor offices, drywall infills will be taking place above the ceiling.  Spray foam will be installed above the ceilings at the exterior wall

Chemistry Update 7 - November 24

Progress

  • Exterior caulking completed on the north, south and east elevations and west elevation
  • 4th floor offices, drywall infills completed above the ceiling.  Spray foam installations completed above the ceilings at the exterior wall
  • 3rd floor offices, drywall infills completed above the ceiling.  Spray foam installations completed above the ceilings at the exterior wall

Upcoming

  • 2nd floor offices, drywall infills will be taking place above the ceiling.  Spray foam will be installed above the ceilings at the exterior wall

Chemistry Update 6 - November 10

Progress

  • Exterior caulking completed on the north, south and east elevations and west elevation

Upcoming

  • 4th floor offices, drywall infills taking place above the ceiling.  Spray foam is being installed above the ceilings at the exterior wall
  • 3rd floor offices, drywall infills taking place above the ceiling.  Spray foam is being installed above the ceilings at the exterior wall

Chemistry Update 5 - November 3

Progress

  • Exterior caulking completed on the north, south and east elevations and west elevation
  • Spray foam insulation of punched windows, and curtain walls has been installed from the exterior of the building on all elevations

Upcoming

  • 4th floor air barrier repairs will continue in the Offices.  Spray foam insulation will be installed around the windows from the interior.  New waterproofing membrane will be installed under the window sills.  Interior caulking will be installed around the window and window sill
  • 4th floor offices, drywall infills taking place above the ceiling.  Spray foam is being installed above the ceilings at the exterior wall
  • 3rd floor offices, drywall infills taking place above the ceiling.  Spray foam is being installed above the ceilings at the exterior wall

Chemistry Update 4 - October 27

Progress

  • Exterior caulking completed on the north, south and east elevations; and nearly complete on the west elevation
  • Spray foam insulation of punched windows, and curtain walls has been installed from the exterior of the building on all elevations

Upcoming

  • 3rd floor air barrier repairs will continue in the Offices.  Spray foam insulation is being installed around the windows from the interior.  New waterproofing membrane is being installed under the window sills.  Interior caulking is  being completed around the window and window sill
  • 4th floor air barrier repairs will continue in the Offices.  Spray foam insulation will be installed around the windows from the interior.  New waterproofing membrane will be installed under the window sills.  Interior caulking will be installed around the window and window sill
  • 4th floor offices, drywall infills taking place above the ceiling.  Spray foam is being installed above the ceilings at the exterior wall

Chemistry Update 3 - October 20

Progress

  • Exterior caulking completed on the north, south and east elevations; and nearly complete on the west elevation
  • Spray foam insulation of punched windows, and curtain walls has been installed from the exterior of the building on all elevations

Upcoming

  • 3rd floor air barrier repairs will continue in the Offices.  Spray foam insulation is being installed around the windows from the interior.  New waterproofing membrane is being installed under the window sills.  Interior caulking is  being completed around the window and window sill
  • 4th floor air barrier repairs will continue in the Offices.  Spray foam insulation will be installed around the windows from the interior.  New waterproofing membrane will be installed under the window sills.  Interior caulking will be installed around the window and window sill

Chemistry Update 2 - October 12

Progress

  • Exterior caulking completed on the north, south and east elevations; and nearly complete on the west elevation
  • Spray foam insulation of punched windows, and curtain walls has been installed from the exterior of the building on all elevations
  • Computer lab punched window air barrier repairs have been completed.  Spray foam insulation has been installed around the windows from the interior.  New waterproofing membrane installed under the window sills.  Interior caulking completed around the window and window sill
  • 2nd floor air barrier repairs are being completed in the Offices.

Upcoming

  • 3rd floor air barrier repairs will continue in the Offices.  Spray foam insulation is being installed around the windows from the interior.  New waterproofing membrane will be installed under the window sills.  Interior caulking to be completed around the window and window sill

Chemistry Update 1 - October 6

Progress

  • Exterior caulking completed on the north, south and east elevations; and nearly complete on the west elevation
  • Spray foam insulation of punched windows, and curtain walls has been installed from the exterior of the building on all elevations
  • Computer lab punched window air barrier repairs have been completed.  Spray foam insulation has been installed around the windows from the interior.  New waterproofing membrane installed under the window sills.  Interior caulking completed around the window and window sill
  • 2nd floor air barrier repairs are being completed in the Offices.

Upcoming

  • 3rd floor air barrier repairs will commence in the Offices.  Spray foam insulation is being installed around the windows from the interior.  New waterproofing membrane will be installed under the window sills.  Interior caulking to be completed around the window and window sill

Chemistry Fume Hood Controls

Glendon

Lumbers

Petrie